Use of Cookies
By continuing your visit on our website, you consent to the use of cookies.
Further information
Close

We use cookies on different pages to make visits of our website attractive and enable use of certain functions. These are small text files stored on your computer. Most of the cookies we use are deleted again from your hard disk after the end of your browser session (so-called session cookies). Other cookies will remain on your computer and make it possible for us to recognise your computer again at your next visit (so-called permanent cookies). Our partner companies have no right to collect personal information via cookies through our website, to process or use them.
INSPIRING TRENCHLESS TECHNOLOGIES

 
Business areas:
Nodig-Systeme
Pipe Bending Systems

TT Group Companies
Int. Sales Partners


If there is no TT representation in your country, please contact the TT headquarters at export@tracto-technik.de or phone +49 2723 808-0
Menu
 

Silent Night Lining with GRUNDOBURST 400S

A GRUNDOBURST 400S was recently used as a pulling device to slipline a 21” cast iron water pipe for a new replacement 450mm SDR17 PE pipe in the Inner City of London.



The relative compact size (L 600mm x W 490mm x D 340mm) and light  weight  of the 400S (200kg) is deceptively small in comparison to the  40 tonne pulling power developed and is ideal for confined space working as well as reducing logistical and jobsite set up costs.

Sliplining_Burst400S_TTUK_03.jpg
GRUNDOBURST 400S and unique QuickLock rods.


To speed up pipe installation times, the longer than usual QuickLock ladder type push/pull rods were used on the night work operation. Due to the highly sensitive London inner city location, the GRUNDOBURST’s Super silenced hydraulic power pack kept noise to a minimum and was greatly appreciated by the local residents.
 

Pushing in the 176 metres of QuickLock rods commenced at 19.30 hours and was completed by 22.30 hours. The sliplined 450mm PE pipe was then connected to the QuickLock rods via a bespoke swivel connection which overcomes any torsional loads being transmitted from the rods to the pipe during installation.

Sliplining_Burst400S_TTUK_02.jpg
The new 450mmPE pipe being sliplined into the host main.


Pull back through the 21” cast iron  water main commenced just after midnight and the new PE pipe arrived unimpaired into the docking frame within four hours. The overall working time included butt fusing the second section of the PE pipe string which took one hour.

Sliplining_Burst400S_TTUK_01.jpg
The new PE pipe and swivel arrives at the docking frame.


An excellent silent and efficient night time pipe installation.
 