Multiple crossings beneath the river Stockacher Aach

01.07.16 - In Stockach, close to the Lake Constance in the District of Constance, Germany, the installation of a new power supply line demanded several crossings beneath the Stockacher Aach, a river flowing from the west of Upper Swabia. To do so, four HDD bores were required which were made using a GRUNDODRILL 25N and a GRUNDODRILL 18ACS drill rig.
New supply pipes for new control centre
The Municipal Works of Stockach operates a power supply system with approximately 4,900 metering points in the centre of the city of Stockach. Roughly 8,000 citizens and 650 customers from commerce and industry are connected to this power supply system. To guarantee a safe and reliable power supply, the Municipal Works has to invest in ongoing maintenance and development of the complex infrastructure, year after year. The installation of a second control unit in the autumn of 2015 was a further significant milestone for the power supply of Stockach.
Until then, the power supply network was connected to the relay station of the BW networks via a control unit. “This control unit was the central supply unit for the complete city centre and provided a reliable service”, explained Tobias Graf, leader of the power supply team. The steady growth of Stockach as a flourishing residential and employment location requires the adaptation of the power supply to the increasing demand. With the installation of a second control unit, the Municipal Works of Stockach has fortified the network, upgrading it for the future.
The new control unit has been built in Stockach in the area of a paper mill. Utilising a 1,500 metre long feed line, it is directly connected to the relay station of the network operator BW networks and now provides a parallel power source for Stockach city centre via two control units. In the long run, this offers the greatest possible safety and reliability of provision to all customers. In addition, the Municipal Works of Stockach provides a higher performance level.

Power Line Route
Over the course of the power line route some sections were completed in open cut and others using HDD (Horizontal Directional Drilling) techniques. The HDD sections were very complex in some parts because it was usually necessary to cross diagonally beneath the river. The construction had to pass beneath part-man-made river banks, weir steps and very environmentally sensitive strips of river bank. The northern side of the river with its wide-looping course forms the border for the industrial and residential building development. The industrial area has also been expanded with artificial fill up to the edge of the northern river bank. Even though the Stockacher Aach should not be mistaken for the larger river, the Radolfzeller Aach situated further to the west and originating from the largest natural spring in Germany, it is still subject to strong seasonal fluctuations of water flow, not unlike its larger neighbour. Short violent water flows quickly alternate with low water time periods. These severe changes of the water flow can occur within a period of just a very few hours. Given the proximity to the buildings, this may lead to drastically changing situations in a flash.

Bore Geology
The Stockacher Aach, along with its little tributary stream within the urban area, the Mahlspürer Aach, flows through coarse crushed terrace rock from the Würm glaciation period. This crushed rock is very coarse and it is usually classified as boulder material, even though the ‘particle’ size may even go beyond this. The origin and composition of this coarse rubble comprises almost the complete spectrum of central to north alpine rock formations. This means that the rocks often have a compressive strength of between 160 and 340 MPa. In particular, the rubble from the Central Alps, of which there is a significant proportion, along with granite, gneiss, amphibolite, diorite, ophiolite, diabase and chert, demonstrates the highest compressive strength values. 
Between the rubble and the smallest blocks of this coarse crushed rock there is also found different sand types. Larger chunks made of molasse sandstone were also found in the bore path. The crushed terrace rock from the Würm glaciation period is highly permeable making it a great challenge when utilising drilling technology. Even with superior rock boring equipment, the drilling control in this coarse crushed rock is no simple task and the high permeability of this Ice Age rubble demands very elaborate borehole support. Bentonite alone is unable to achieve the required stability for the large upsizing diameters, therefore eco-friendly polymer additives are used to support the borehole.

HDD operations beneath and along the river Stockacher Aach
The renowned HDD technology contractor Maier Bau was granted the contract to undertake a total of four ‘double’ HDD operations (two parallel bores each with a space of approximately 1.5 m in between each set) beneath the Stockacher Aach and along its bank. The drilling operations comprised several sections for the installation of the required pipe including:
  • two double fluid-assisted bores of each about 150 m length, pulling a bundle of 3 x 140 mm OD pipe and 1 x 50 mm OD pipe, with on a parallel course to the first bore and with a space of 1.5 m in between, a second bundle with 2 x 160 mm OD pipe and 1 x 50 mm OD pipe
  • two further double fluid-assisted bores in each about 140 m length, pulling a bundle of 2 x 160 mm OD pipe and 1 x 50 mm OD pipe, again parallel to another bundle of 3 x 140 mm o.d. pipe with 1 x 50 mm OD pipe. The total bore length over all the installations exceeded 500 metres.
To achieve the installations, two drilling rigs were used. The first was a GRUNDODRILL 25 N drill rig (which was used for three of the bores) and secondly a GRUNDODRILL 18 ACS drill rig (which was used for one bore), both machines were.
For the pilot bores, which required approximately 6 to 10 working hours each to complete, hard drill heads manufactured by Tracto-Technik were put to use. The minimum cover beneath the riverbed was predefined at 1.5 metres. In the event a cover of at least 2 metres was finally achieved. Upsizing of the pilot bore holes was carried out in three steps. Step one with a cone reamer of 250 mm diameter, step two required a cone reamer of 350 m diameter and, finally a cleaning run with a 380 mm diameter smoothing reamer. Each upsizing step took about 6 hours in the coarse rubble material. The pipes were pulled in as bundles as described above, with the larger pipes designed to accommodate the single conductor lines of the new medium voltage cable and glass fibre control and data lines being pulled into the accompanying 50 mm diameter pipe. With the exception of sandstone obstacles close to the weir steps of the Stockacher Aach which somewhat slowed down the drilling routine, all drilling jobs were carried out successfully and on schedule, in spite of the really difficult geology of the site. After four weeks of drilling, all four bore paths were passed over to the land surveyor crew of the municipal works for initial measurement. 
News-Overview

DO YOU HAVE ANY QUESTIONS?

WE WILL BE GLAD TO HELP YOU!

YOU CAN REACH US
BY PHONE FROM
MONDAY TO FRIDAY
07:00 TO 17.00 O'CLOCK!

CALL US!

SEND US A MESSAGE
AND WE WILL GET BACK
TO YOU!

WRITE TO US!
Contact

Do you have any product or
services related questions?

Please contact us:

+49 2723 808-0

SEND E-MAIL
X

Privacy settings

We use cookies on our website. Some of them are essential to operate the website, while others help us analise the use of our website and improve our services. By clicking on "I accept" you agree to the processing of your data. You can use the "Individual cookie settings" button to refuse the use of cookies or to customise them at any time. You will find more detailed information in our data protection declaration.

Necessary
Statistics
Marketing
Accept all

Only accept necessary cookies
Individual cookie settings
Privacy statement | Legal notice

Privacy settings

X
Here you will find an overview of all cookies used. You can give your consent to the categories and display further information.
Accept all Back Store

Necessary>

Cookie
autokat
Cookie assist to provide the category for the download area.
autopg
Cookie assist to provide the product group for the download area
autop
Cookie assist to provide the product for the download area
tt_c_req
Consent to the use of necessary cookies. This figure can not be altered. If you don't store this figure, we can't allow you to access this page.
tt_c_stat
Consent or disapproval of cookies to create statistics
tt_c_marketing
Consent or disapproval of cookies for market analysis. Integrated Youtube-Videos can only be played with consent.
cftoken
This cookie is used to determine the type of device the guest is using, so that the website can be correctly formatted. This information is stored inside cookie "CFID".
cfid
This cookie is applied in connection with the cookie "cftoken". The cookie stores a specific ID for the guest, as well as the device and browser of the guest.
c_domIDPrefix
Cookie assist to store the chosen domain.
c_domIDSuffix
Cookie assist to store the chosen domain.
c_login
Cookie assist to store the login-data.
cfglobals
Is defined by Adobe ColdFusion to identify the client device, so that the website-user-session variations can be stored.

Statistics>

Cookie
_ga
Registers a unique ID, which is applied to generate statistical information, showing how the visitor uses the site.
_gat
Is applied by Google Analytics to restrict the requirement rate.
_gid
Registers a unique ID, which is applied to generate statistical information, showing how the visitor uses the site.

Marketing>

Cookie
ads/ga-audiences
Used by the Google Tag-Manager.
gps
Registers a unique ID on mobile devices, to enable tracking based on the geographic GPS location.
ide
Applied by Google DoubleClick to register and report the users actions on the website after viewing or clicking on one of the providers ads, for the purpose of measuring the effectiveness of an advertisement and displaying targeted advertising to the user.
pref
Registers a unique ID, applied by Google to obstain statistics on how visitors use YouTube-Videos on various websites.
test_cookie
Used to check whether the visitors browser supports cookies.
VISITOR_INFO1_LIVE
Tries to estimate the user bandwidth on pages with integrated YouTube-Videos.
YSC
Registers a unique ID to keep statistics of YouTube videos, which the user has seen.
yt-remote-cast-installed
Stores the user settings when retrieving a Youtube-Video integrated on other websites.
yt-remote-connected-devices
Stores the user settings when retrieving a Youtube-Video integrated on other websites.
yt-remote-device-id
Stores the user settings when retrieving a Youtube-Video integrated on other websites.
yt-remote-fast-check-period
Stores the user settings when retrieving a Youtube-Video integrated on other websites.
yt-remote-session-app
Stores the user settings when retrieving a Youtube-Video integrated on other websites.
yt-remote-session-name
Stores the user settings when retrieving a Youtube-Video integrated on other websites.
CTCNTNM_a8a9cd6e100ea022
Cookie from wireminds GmbH to analise visitor behaviour. This may involve the collection, processing and storage of data from which user profiles are created under a pseudonym.
track
Cookie from wireminds GmbH to analise visitor behaviour. This may involve the collection, processing and storage of data from which user profiles are created under a pseudonym.